With the improvement of the market situation, more and more investors are starting to opt to invest in and construct charging stations. However, for many people, this is a brand-new industry and an unfamiliar market, and they not very clear about the investment process and operation qualification s . Therefore, Maruikel est once again shar ing the details of the construction process of the "charging station" that was previously released.
Generally speaking, there are six steps to invest in and construct a charging station: preparatory work → filing → land review → planning review → electricity application → acceptance and confirmation .
Before determining the investment and construction , it is necessary to inspect the candidate sites, such as open spaces and parking lots, and sign a cooperation agreement with the site owners on the construction of charging stations. According to the actual situation of the site and traffic flow, the construction scale and the number of charging piles are determined. At the same time, we should also make a project budget.
1. I t is recommended that the site be in a parking space or a greening parking space ;
2. Parking spaces should not be too tight and should be open to the public;
3. The entrances and exits of the parking spaces should be convenient to avoid traffic jams ;
4. Areas near business districts, high-speed railway stations, railway stations, urban main roads, etc. can be given priority .
F il ing
After the preliminary preparatory work is completed, you can go to the provincial and municipal regulatory platforms for filing, and then submit the materials to the local development and reform commission. After passing the examination and approval of various departments, you can obtain the registration certificate.
Land Review
After obtaining the registration certificate, you can go to the Bureau of Land and Resources for a review of the legality of the land to clarify the land nature and property rights ownership .
Planning Review
After clarifying the legality of the target land, go to the Planning Bureau for a review of land use to confirm that the government has no other plans for the site in the next few years .
Electricity Application
Once all the preparations are in place, investors can bring the materials obtained from the above processes to the Electric Power Bureau for application. The Electric Power Bureau will review the above materials. After the review is completed, relevant documents will be issued, and then construction can begin .
The specific process of power application and the required materials are as follows:
The application materials include:
Written application, copy of project approval (for new building), factory site plan, original and copy of planning red line map, applicant's identity certificate (original and copy), business license, legal person qualification certificate (original and copy), land use certificate, etc.
The materials provided include:
Power supply plan reply sheet, design power of attorney, and list of electrical equipment.
The design drawings must be submitted to the power supply company for examination and approval, and a Drawing Examination Opinion can be issued before the material procurement and engineering construction can be organized, otherwise the power supply company will not be able to accept the power connection.
The application materials include:
(1) Product qualification instructions for the equipment ;
(2) Test records and installation technical records (including hidden project records );
(3) Completion drawings and construction instructions (construction technical measures);
(4) Electrical part design drawings and design change letters with the review opinions of the power supply company ;
(5) Information and records deemed necessary by the power supply enterprise;
(6) The electrical part completion drawings shall be completed within one month after the power transmission of the project and submitted to the power supply company for filing;
(7) The power supply company shall complete the on-site acceptance within 5 working days after accepting the completion report.
(1) A copy of the business license;
(2) Legal person qualification certificate (or power of attorney);
(3) Tax registration number, opening bank and account number;
(4) The original and photocopy of the on-grid operation license of the duty electrician.
Purchase of Charging Piles
Quotation for Charging Pile Construction
Acceptance C onfirmation
After the construction of the charging station is completed, the power company will conduct acceptance inspection, including signs, signboards, fire-fighting equipment and so on. After the acceptance, the power will be turned on, and then a third-party testing agency will test the charging piles and issue a corresponding test report. After that, it can be put into operation.
Operation of Charging Piles
The above are the main processes for investing in and constructing a charging station ! However, the policies of each place may be different, and the specific problems will be analyzed in detail. It is recommended that investors must have a detailed understanding of the policy situation in the project location before preparing for the project investment and construction. .
Of course, if investors pursue a more perfect charging station with better user experience, they can also consider customizing awnings, drivers' lounges, vending machines, fast food restaurants, self-service car washing docking, etc., and equipped with supporting facilities for charging stations. Of course, whether to choose supporting facilities or which supporting facilities to choose depends on the actual situation of investors.